The Geotechnical Risk Data Center Developers Find Too Late

Reading Time: 3 minutes

By Peter Nabhan, ECS Director of Digital Infrastructure Markets 

Early in my career, I worked on a group of Americans with Disabilities Act (ADA) improvement projects for a large institutional owner. The design was done, and the owner had already spent real money on soft costs (about 10% of overall project cost). Then construction pricing came in. Design recommendations became so conservative that costs kept climbing, and the owner stopped the projects because the numbers no longer worked.  

That experience changed how I think about my work in geotechnical engineering. It’s important to stay true to the science of the practice and recognize that a geotechnical recommendation is also a financial decision, whether it’s typically treated that way or not. 

Today much of my work is in data centers, and I see the same lesson at a much larger scale. 

Where the geotechnical risk hides 

When developers look for a data center site, they optimize for power, water, fiber and land availability. That order makes sense, because a site without power cannot support the project. The problem is that the geotechnical review often comes after those decisions are made. By then, the land is under contract or already purchased and the pro forma rests on assumptions nobody on the geotechnical side has tested. 

This is when surprises can get expensive. A site that needs a deep foundation system instead of shallow foundations may still be a good site. But if the developer learns this after closing, the cost lands on a budget that was never sized for it. Conditions like karst environments can create the same kind of surprise. Not every developer misses this, but some do. 

At ECS, my team and I saw this on a project that carried a very limited geotechnical scope through design. Once construction started, the soils turned out to be unsuitable for the planned foundation and the client brought in ECS to redesign for a deep foundation system. The project was completed successfully, but it cost months of delay and a redesign nobody had budgeted. 

Why this is our problem too 

It is easy for geotechnical engineers to take a back seat and let other designers, like architects, for instance, walk the client through risk. That leaves value on the table. Even though our contract often sits under a design professional, the developer is ultimately the client, and we should be able to communicate geotechnical risk at that level, so it’s well understood.  

Every developer is optimizing a different variable. Some are risk-averse, others need the project online as fast as possible and some are capital-constrained. The biggest gap I see between engineers and developers is the belief that one answer fits every client. It does not. 

On a data center, because demand far exceeds supply, schedule usually drives the decision. Imagine a foundation option that costs $2 million more but saves a month in construction schedule. If a month of delay costs the owner more than $2 million of lost revenue, the more expensive option is the better investment. We can only make that case if we understand what drives the client’s decision.  

What I ask engineers to do 

First, get into the conversation earlier. The earlier we look at the subsurface, the more options the developer can evaluate. 

Second, learn how your recommendations turn into cost and schedule. That knowledge makes your technical judgment far more useful, not less. 

Third, work alongside the developer, not only the design team. Understand their priorities and help them see the full risk picture so they can decide what risk they are willing to accept. 

Site selection is changing. Power and water decide where a data center can go. Geotechnical conditions help decide what it costs to build there and how long it takes. Engineers who can speak to both will be the ones developers want at the table from day one.