AP Moeller-Maersk Terminal, Portsmouth, VA |
![]() Project Description: The new shipping terminal is a $200 million, 400 acre facility on the ECS Involvement: ·
Provided
observation of reinforcing steel and concrete sampling and testing for
foundation systems, and appurtenant equipment foundations ·
Provided
observation and testing of all subgrade, subbase, and pavement systems ·
Performed
transport, laboratory curing, and compressive strength testing for cylinder
specimens ·
Performed
contractor's QC for all trades ·
Performed
soil proctor and acceptability tests for proposed borrow material for fill ·
Observed
building envelope systems including precast and window walls for bolted and
welded structural connections |